Small scale permit issuance process

  • Provision of the necessary documents, which are:
  1. Owner’s Application.
  2. Application form about the conducted operations.
  3. Reasoned technical report.
  4. Building permit copy.
  5. Ownership title with the accompanying plat.
  6. Solemn statement of the law 1599/86, if the construction was built before 1955.

  • New measurement of the land provided it concerns operations in a plot of land and not a building.
  • Operations report, if necessary.
  • Authorization by the archaeology service/forest inspectorate/ministry of agriculture, if necessary.